In the given figure, the network of a project represents
activity of an excavation of a footing
activity of an excavation which starts at event No. 1 and ends at even No. 2
activity of excavation which takes 8 units of time
none of these.
Correct Answer:
activity of excavation which takes 8 units of time
← Previous Question
Next Question→
More Questions from
Construction Management
Mile Stone charts were invented in the year of
The estimated time required to perform an activity, is known as
Time and progress chart of a construction, is also known as
The first method invented for planning projects, was
The difference between the time avail-to do a job and the time required to do the job, is known as
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
A critical ratio scheduling
A Milestone chart
Pick up the incorrect statement from the following:
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be