Difficulty: Easy
Correct Answer: Minor projects
Explanation:
Introduction / Context:
Cost thresholds are used in public works to categorise jobs for administrative control, sanctioning powers, and procedure. This classification guides tendering, supervision, and reporting levels.
Given Data / Assumptions:
Concept / Approach:
Small-value works are commonly grouped as minor projects/works, attracting simpler procedures and lower sanctioning levels compared to major projects. While exact thresholds can vary by department and time, exam standards usually map sub-Rs. 20,000 works to the minor category.
Step-by-Step Solution:
Identify conventional categories: major vs minor.Map the small cost value to the minor class.Select Minor projects.
Verification / Alternative check:
Older CPWD/state PWD manuals and standard exam prep sources treat small-ticket works as minor; confirm with the latest departmental schedule when applying in practice.
Why Other Options Are Wrong:
Common Pitfalls:
Assuming uniform thresholds across departments or years; ignoring that exam questions use conventional legacy thresholds for pedagogy.
Final Answer:
Minor projects