Difficulty: Easy
Correct Answer: Duration
Explanation:
Introduction / Context:
Precise terminology underpins CPM/PERT analysis. Confusing duration, float, events, and dummies leads to planning and control errors. This question checks the exact term for the time needed to execute an activity.
Given Data / Assumptions:
Concept / Approach:
Duration is the planned time for an activity from its start to its finish. It is distinct from float (schedule flexibility), an event (a point in time marking start/finish), or a dummy (a zero-duration logical connector in AOA networks).
Step-by-Step Solution:
1) Identify the quantity described: time needed to do the work.2) Map to definitions: duration = required time; float = allowance; event = node; dummy = zero-time logic.3) Conclude the correct term is duration.
Verification / Alternative check:
Standard CPM/PERT texts define activity time as duration; float is derived later from early/late times and critical path calculations.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
Duration.
Discussion & Comments