In PERT, if a is the optimistic time, b is the pessimistic time, and m is the most likely time of an activity, what is the expected time (te)?

Difficulty: Easy

Correct Answer: te = (a + 4m + b) / 6

Explanation:


Introduction / Context:
PERT (Program Evaluation and Review Technique) models activity duration uncertainty using three estimates: optimistic (a), most likely (m), and pessimistic (b). The expected time te is a weighted mean that emphasizes the most likely value while still incorporating extremes.


Given Data / Assumptions:

  • Optimistic time = a
  • Most likely time = m
  • Pessimistic time = b
  • Distribution is approximated by a Beta distribution on the activity's range [a, b].


Concept / Approach:
PERT uses a weighting scheme that gives four times the weight to the most likely estimate, producing te = (a + 4m + b) / 6. This balances realism (m) with risk bounds (a and b).


Step-by-Step Solution:
Identify the PERT expected time formula.Write it using standard keyboard symbols:te = (a + 4*m + b) / 6Compare against options to find the match.Select option with (a + 4m + b) / 6.


Verification / Alternative check:
Variance is often computed as sigma^2 = ((b - a) / 6)^2, consistent with the same weighting logic used for te.


Why Other Options Are Wrong:

  • (a + b + m) / 3: Simple average, ignores heavier weight for m.
  • (2a + m + 3b) / 6 and (a + 2m + b) / 4 and (4a + m + b) / 6: Incorrect weightings; they misrepresent the Beta-based heuristic.


Common Pitfalls:
Using an unweighted mean; swapping weights between a and b; forgetting the denominator 6 tied to 1 + 4 + 1 weighting.



Final Answer:
te = (a + 4m + b) / 6

More Questions from Construction Management

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion