In scheduling, the difference between the time available to do a job and the time actually required for that job is called float (slack).

Difficulty: Easy

Correct Answer: Float

Explanation:


Introduction / Context:
Float (also called slack) is central to CPM-based control because it quantifies schedule flexibility. This question checks if you can distinguish float from duration, events, and constraints.


Given Data / Assumptions:

  • Time available vs time required is given.
  • We must name that difference appropriately.


Concept / Approach:
Float represents the permissible delay in an activity without affecting specific schedule targets (e.g., project finish, successor earliest starts). Unlike duration (time needed to do work), float is schedule leeway derived from early/late event times in CPM analysis.


Step-by-Step Solution:
1) Identify the definition: available time minus required time.2) Map to standard terms: that difference is float/slack.3) Confirm that duration is the required time itself, not the difference.4) Conclude the correct term is float.


Verification / Alternative check:
CPM computations of total float and free float follow from forward/backward passes and early/late times, capturing this difference formally.


Why Other Options Are Wrong:

  • Event: A point in time; does not quantify a difference.
  • Duration: The needed time, not extra allowance.
  • Constraint: A rule/limit (e.g., must-start-on) rather than a time difference.


Common Pitfalls:

  • Treating float as a buffer to be consumed casually, risking loss of schedule protection.
  • Confusing float with reserve or contingency added to duration estimates.


Final Answer:
Float.

More Questions from Construction Management

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion