Difficulty: Medium
Correct Answer: All of the above
Explanation:
Introduction / Context:
Critical Ratio (CR) scheduling is a dispatching/priority technique used in project and production environments to decide what to work on next. It relies on a ratio that blends schedule urgency with remaining workload, and it updates as conditions change. This question checks your understanding of what CR achieves in practice.
Given Data / Assumptions:
Concept / Approach:
Because CR is computed with current remaining time and effort, it naturally creates comparable priorities across activities, reveals whether a task is ahead or behind schedule, and changes as progress or estimates change—hence it is dynamic rather than static.
Step-by-Step Solution:
1) Compute CR for each activity using current remaining time and work.2) Rank activities by CR: the smallest CR is most urgent.3) Interpret CR value to assess status: CR < 1 behind schedule; CR ≈ 1 on track; CR > 1 ahead.4) Recalculate as progress reports update → priorities adapt automatically.
Verification / Alternative check:
Run a simple example with two activities; recompute CR after logging progress. Observe priority changes and status signals aligning with expectations.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
All of the above.
Discussion & Comments