Difficulty: Easy
Correct Answer: All the above.
Explanation:
Introduction / Context:
CPM and PERT are canonical network techniques in project management. Knowing their orientation and assumptions guides method selection, interpretation of floats, and risk handling.
Given Data / Assumptions:
Concept / Approach:
CPM (Critical Path Method) is activity-oriented and assumes deterministic durations; it also supports time–cost optimisation (crashing). PERT (Program Evaluation and Review Technique) is event-oriented and models duration uncertainty using a, m, b with expected times.
Step-by-Step Solution:
Evaluate A: True—CPM focuses on activities.Evaluate B: True—PERT historically emphasises events and probabilistic times.Evaluate C: True—CPM uses single (deterministic) durations.Evaluate D: True—CPM includes time–cost trade-off analyses (crashing).Therefore E (All the above) is correct.
Verification / Alternative check:
Textbook comparisons of CPM vs PERT consistently list these differences and capabilities.
Why Other Options Are Wrong:
Common Pitfalls:
Assuming PERT and CPM are interchangeable; forgetting time–cost trade-off is more closely tied to CPM.
Final Answer:
All the above.