In project scheduling terminology, the estimated time required to perform a specific activity is called its duration.
-
AEvent
-
BDummy
-
CDuration
-
DFloat
Answer
Correct Answer: Duration
Explanation
Introduction / Context:Precise terminology underpins CPM/PERT analysis. Confusing duration, float, events, and dummies leads to planning and control errors. This question checks the exact term for the time needed to execute an activity.
Given Data / Assumptions:
- An activity has an estimated completion time under normal conditions.
- We must name that quantity correctly.
Concept / Approach:Duration is the planned time for an activity from its start to its finish. It is distinct from float (schedule flexibility), an event (a point in time marking start/finish), or a dummy (a zero-duration logical connector in AOA networks).
Step-by-Step Solution:1) Identify the quantity described: time needed to do the work.2) Map to definitions: duration = required time; float = allowance; event = node; dummy = zero-time logic.3) Conclude the correct term is duration.
Verification / Alternative check:Standard CPM/PERT texts define activity time as duration; float is derived later from early/late times and critical path calculations.
Why Other Options Are Wrong:
- Event: Instant in time, not a span.
- Dummy: Has no time; indicates logic only.
- Float: Not required time, but schedule leeway.
Common Pitfalls:
- Using float and duration interchangeably.
- Assuming dummy activities consume time.
Final Answer:Duration.