Difficulty: Easy
Correct Answer: all the above
Explanation:
Introduction / Context:
Critical Path Method (CPM) networks distinguish activities that directly control the project duration (critical) from those with float (noncritical). Recognizing this allows targeted control and proactive risk management.
Given Data / Assumptions:
Concept / Approach:
Network analysis computes earliest and latest times and derives floats. Activities on the longest path (critical path) determine the project finish date. Any delay on this path delays the entire project; hence attention, monitoring, and resources should prioritize these activities.
Step-by-Step Solution:
1) Identify critical activities by zero float.2) Monitor them more frequently and assign experienced crews/resources.3) If noncritical tasks are ahead or comfortably within float, shift resources temporarily to critical tasks.4) Maintain vigilance: preventing slippage on critical activities prevents project slippage.
Verification / Alternative check:
Update the network periodically; if floats shrink or change, priorities must adjust. Earned-value or progress indices can cross-check that attention is indeed focused where schedule risk is highest.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
all the above.