In a project network, the artificial activity used solely to show dependency (that a following activity cannot start until a preceding one is complete) is called:
-
Aevent
-
Bfree float
-
Cdummy
-
Dconstant
Answer
Correct Answer: dummy
Explanation
Introduction / Context:Network techniques (PERT/CPM) sometimes require artificial constructs to express logic without implying real work or time consumption. Understanding these constructs ensures correct dependency modeling.
Given Data / Assumptions:
- The activity in question indicates only precedence, not real work.
- It carries zero duration and zero resource needs.
- Its purpose is to maintain correct logical relationships and network integrity.
Concept / Approach:A dummy activity is a zero-duration connector used in Activity-on-Arrow (AOA) networks to preserve logic when two activities share some but not all predecessors, or when unique identification of relationships is needed.
Step-by-Step Solution:Step 1: Differentiate real activities (with duration) from artificial links (no duration).Step 2: Recognize that an “event” is a node (milestone), not an activity.Step 3: Identify “dummy” as the artificial, zero-time activity used to express precedence only.
Verification / Alternative check:Classic PERT/CPM AOA notation depicts dummy as a dashed arrow with duration = 0 to represent pure dependency.
Why Other Options Are Wrong:
- event: A milestone node, not an activity.
- free float: A scheduling parameter (slack), not an activity.
- constant: Not a standard term in network modeling.
Common Pitfalls:Assigning time or resources to dummies; confusing dummies with actual work or with float/slack concepts.
Final Answer:dummy