Which of the following best represents a project activity in scheduling and network analysis?

Difficulty: Easy

Correct Answer: all the above.

Explanation:


Introduction / Context:
In project scheduling, an activity is a time-consuming task that transforms inputs into outputs and advances the project toward completion. Recognizing activity statements helps in correctly building WBS and networks.



Given Data / Assumptions:

  • Options include tasks from construction and general contexts.
  • Each statement describes work that takes time and resources.
  • We must identify which statements qualify as activities.


Concept / Approach:
An activity must have a start, a finish, and a measurable duration. It may require labour, equipment, and materials. The domain can vary (construction, education, household), but the definition remains the same.



Step-by-Step Solution:
Step 1: excavation for foundation: Clearly a construction activity with quantifiable duration and resources.Step 2: curing of concrete: A time-bound process (e.g., 7–28 days) and therefore an activity in schedules.Step 3: setting of question paper: A knowledge-work activity with a defined deliverable and duration.Step 4: preparation of breakfast: A valid example of an activity outside construction; still meets the definition.Step 5: Therefore, all listed items represent activities.



Verification / Alternative check:
Any task with start/finish and non-zero duration qualifies as an activity in network or bar-chart scheduling.



Why Other Options Are Wrong:

  • Picking any single task ignores that all listed tasks meet the formal definition.


Common Pitfalls:
Confusing events (instantaneous milestones) with activities (time-consuming tasks) or assuming only construction examples count.



Final Answer:
all the above.

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion