Pick up the correct statement from the following:
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurence time
Maximum value of earliest expected time is used if there are more than one value of any event
Minimum value of latest occurrence time is used if there are more than one value of any event
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Construction Management
The main disadvantage of line organisation, is
Pick up the incorrect statement from the following:
For completion of a project, the critical path of the network represents
Pre-tender stage requires
Frequency distribution curves
The first stage of a construction, is
Pick up the correct statement from the following:
Pick up the correct statement from the following:
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Pick up the correct statement from the following: