Critical Path Method (CPM): In a project network, the critical path represents which of the following for overall project completion?

Difficulty: Easy

Correct Answer: minimum time

Explanation:


Introduction / Context:
Critical Path Method (CPM) identifies the longest path of dependent activities in terms of duration. This path determines the shortest possible time in which a project can be completed because any delay on the critical path directly delays project finish.



Given Data / Assumptions:

  • A network of activities with deterministic durations.
  • Logical precedence constraints are respected.
  • No resource constraints are considered in the baseline CPM calculation.


Concept / Approach:
The critical path is the path with zero total float and the greatest cumulative duration among all paths. Project duration equals the duration of this path; thus it represents the minimum achievable completion time given current logic and durations.



Step-by-Step Solution:
List all start-to-finish paths.Sum durations along each path.Identify the path with the greatest sum; this is the critical path.Project completion time equals this sum; therefore it is the minimum feasible time unless logic or durations change.


Verification / Alternative check:
Forward pass gives earliest finish of the final event; backward pass confirms zero float on critical activities. Any compression must target critical activities (crashing) to reduce project duration.



Why Other Options Are Wrong:

  • Maximum time: misleading; the critical path duration is the minimum achievable project completion time.
  • Maximum/minimum cost: CPM by itself does not determine cost.
  • Maximum float: critical path has zero float.


Common Pitfalls:
Confusing 'longest path' in duration with 'maximum time' as a goal; assuming that noncritical activities can be delayed without consequence beyond their float.



Final Answer:
minimum time

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion