The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is

Civil Engineering Construction Management
Choose an option
  • A
    19
  • B
    14
  • C
    24
  • D
    None of these.

Answer

Correct Answer: 19