Difficulty: Easy
Correct Answer: Programme Evaluation and Review Technique (PERT) is event-oriented
Explanation:
Introduction / Context:
PERT and CPM are classic network-based planning tools. Understanding their focus helps practitioners select the right tool for uncertain R&D-type projects vs. repetitive construction with known activity durations.
Given Data / Assumptions:
Concept / Approach:
PERT charts were historically 'event-oriented,' indexing nodes as events and computing expected times using optimistic, most likely, and pessimistic estimates. CPM, developed for construction/maintenance, is activity-oriented with cost–time trade-off (crashing) emphasis.
Step-by-Step Solution:
Identify PERT: events (nodes) mark the completion of preceding activities; uncertainty modeled with beta assumptions.Identify CPM: activities (arrows/bars) with deterministic durations; cost-curves enable crashing.Therefore, the correct distinguishing statement is that PERT is event-oriented.
Verification / Alternative check:
Most textbooks contrast Activity-on-Arrow PERT diagrams (event emphasis) with Activity-on-Node CPM diagrams (activity emphasis), even though modern software often uses AON for both.
Why Other Options Are Wrong:
Common Pitfalls:
Assuming PERT and CPM are interchangeable; ignoring that risk buffers and three-time estimates are central to PERT but not CPM.
Final Answer:
Programme Evaluation and Review Technique (PERT) is event-oriented