For the network shown in the given figure, the expected time for the activity
Civil Engineering
Construction Management
Choose an option
-
A1-2 is 4
-
B2-3 is 7
-
C3-4 is 8
-
Dall the above.
Answer
Correct Answer: all the above.
Explanation
Expected time = (Pessimistic value + 4*most likely value + Optimistic value)/6.
1-2 is 4.
2-3 is 7.
3-4 is 8.