Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
20
25
35
15
Correct Answer:
25
← Previous Question
Next Question→
More Questions from
Construction Management
Classification in construction management: How are residential buildings generally categorized? In construction planning and estimation, residential buildings (houses, apartments, hostels) are typically treated as which class of construction based on size, loading, and resource intensity?
Project classification: Railway projects are treated as what type of construction? In civil engineering project management, how are railway projects (permanent way, yards, bridges, station works) typically categorized based on scale and resource intensity?
PERT/CPM notation: How is an event represented on a network diagram? In activity-on-arrow (AOA) or activity-on-node (AON) conventions, the event (milestone) is indicated by a number enclosed in which geometric shape?
Float characteristics on the critical path In Critical Path Method (CPM), a critical activity’s float value is equal to what?
Independent float formula with clear event times For an activity i→j of duration t, let L_i be the latest event time at its start (tail) and E_j be the earliest event time at its finish (head). If we denote t1 = L_i and t2 = E_j, what is the independent float (IF)?
Scheduling a project by CPM: What are the essential steps? When preparing a CPM schedule for an engineering project, which set of actions correctly describes the overall process?
Project classification: How are power stations generally treated? Considering typical scope (civil, structural, mechanical, electrical, and control systems), a power station falls under which class of construction project?