Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Home
»
Civil Engineering
»
Estimating and Costing
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
1.5 m3
2.5 m3
3.5 m3
5.0 m3
Correct Answer:
5.0 m3
← Previous Question
Next Question→
More Questions from
Estimating and Costing
Pick up the item whose weight is added to the weight of respective item, is
The cross-sectional area of the embankment of a canal fully in embankment in the given figure is
Referring of given figure, pick up the correct statement from the following:
Size, capacity and materials need be specified for
Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
Pick up the correct statement regarding the centre line method of estimating a building
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended
The measurement is made for stone work in square metre in case of
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments