Civil engineering estimation — trigger for revised estimate due to price level change: As per standard departmental practice, a revised estimate must be prepared if the sanctioned estimate exceeds the original because of price level change by more than what percentage?

Difficulty: Easy

Correct Answer: 5.0%

Explanation:


Introduction / Context:
Cost control in public works relies on thresholds that trigger a revised estimate. When prices escalate, the sanctioned cost may exceed the technically sanctioned (TS) estimate, requiring administrative review and re-approval to maintain financial discipline.


Given Data / Assumptions:

  • Only price level (market rates) is changing; scope and quantities remain the same.
  • Departmental rules commonly prescribe a threshold percentage.
  • Question asks the standard percentage value used as a trigger.


Concept / Approach:

Departments typically set a clear percentage (commonly 5%) beyond which a revised estimate becomes mandatory to reflect current schedule of rates and secure proper sanction for the increased outlay.


Step-by-Step Solution:

1) Identify intent: escalation-only situation.2) Apply standard threshold used in PWD/CPWD-style practice.3) Select 5.0% as the commonly adopted trigger for revised estimate due solely to price change.


Verification / Alternative check:

Many exam standards and departmental guides cite 5% as the limit before revising the estimate because of rate revisions.


Why Other Options Are Wrong:

  • 2.0%, 2.5%, 4.0% are too low and would cause frequent administrative burden without material benefit.
  • “—” is not a valid engineering control value.


Common Pitfalls:

  • Confusing escalation triggers with scope-change triggers (which may require revision regardless of percentage).
  • Using provisional sums without updating SORs.


Final Answer:

5.0%.

More Questions from Estimating and Costing

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion