Civil engineering estimation — trigger for revised estimate due to price level change: As per standard departmental practice, a revised estimate must be prepared if the sanctioned estimate exceeds the original because of price level change by more than what percentage?
-
A2.0%
-
B2.5%
-
C4.0%
-
D5.0%
-
E—
Answer
Correct Answer: 5.0%
Explanation
Introduction / Context:Cost control in public works relies on thresholds that trigger a revised estimate. When prices escalate, the sanctioned cost may exceed the technically sanctioned (TS) estimate, requiring administrative review and re-approval to maintain financial discipline.
Given Data / Assumptions:
- Only price level (market rates) is changing; scope and quantities remain the same.
- Departmental rules commonly prescribe a threshold percentage.
- Question asks the standard percentage value used as a trigger.
Concept / Approach:
Departments typically set a clear percentage (commonly 5%) beyond which a revised estimate becomes mandatory to reflect current schedule of rates and secure proper sanction for the increased outlay.
Step-by-Step Solution:
1) Identify intent: escalation-only situation.2) Apply standard threshold used in PWD/CPWD-style practice.3) Select 5.0% as the commonly adopted trigger for revised estimate due solely to price change.Verification / Alternative check:
Many exam standards and departmental guides cite 5% as the limit before revising the estimate because of rate revisions.
Why Other Options Are Wrong:
- 2.0%, 2.5%, 4.0% are too low and would cause frequent administrative burden without material benefit.
- “—” is not a valid engineering control value.
Common Pitfalls:
- Confusing escalation triggers with scope-change triggers (which may require revision regardless of percentage).
- Using provisional sums without updating SORs.
Final Answer:
5.0%.