Estimating and Costing Questions
Practice Estimating and Costing MCQs with answers and explanations. Page 1 of 5.
Category
Civil Engineering
Topic
Estimating and Costing
Page
1 / 5
Mode
Practice
Questions
Open any question to view the answer and explanation.
For 12 mm thick cement plaster in proportion 1 : 6 applied over 100 m^2 of new brickwork, estimate the quantity of cement required (express the answer in cubic metres of loose cement, considering standard allowances).
Open
View answer
In reinforced concrete (R.C.C.) beam detailing, which statements about bent-up bars near supports are correct with respect to resisting negative bending moment, sharing (shear) force, and the typical bend angle?
Open
View answer
In earthwork volume computation, the trapezoidal formula relies on which fundamental assumption(s) about the geometry of the end sections and area variation?
Open
View answer
Regarding a house sewer intercepting device (master trap) and its fresh-air inlet arrangement, identify the incorrect statement from typical public health engineering practice.
Open
View answer
In earthwork estimation using the mid-section (mean-section) method, which of the following statements correctly describe how areas and volumes are determined between two consecutive sections?
Open
View answer
In building measurements and billing, which of the following steelwork items are typically measured in square metres (sq.m)?
Open
View answer
In earthwork/payment classification, which excavation items are measured in square metres (sq.m) rather than cubic metres (cu.m)?
Open
View answer
In building measurements (quantity surveying), what is the conventional order of booking dimensions for items such as masonry, concrete, and plaster?
Open
View answer
In a brickwork Bill of Quantities (BOQ), which of the following items is typically measured in square metres (sq.m) rather than cubic metres (cu.m) or running metres?
Open
View answer
According to standard productivity norms, what is the expected out-turn (area completed) for a 2.5 cm thick cement concrete floor per mason per day?
Open
View answer
In measurement and estimation for building services, which of the following statements regarding water-supply pipe items is correct: separate measurement of trench-laid versus wall-fixed pipes, inclusion of cutting through walls/floors with the pipe item, classification of pipes by size/quality, and explicit specification of jointing/fixing method?
Open
View answer
According to standard methods of measurement used in civil engineering estimation, the volume of work items (e.g., earthwork, concrete) shall be recorded correct to the nearest which value?
Open
View answer
While preparing a detailed estimate for civil works, specify the required recording precision for each quantity: dimensions (length), areas, and volumes to be entered in the measurement book.
Open
View answer
In the design of household sanitation, what is the minimum internal width typically adopted for a septic tank to ensure maintainability and structural practicality?
Open
View answer
In public works accounting and estimation, identify the correct definitions: work value (excluding contingencies and establishments), actual cost (including incidentals), administrative approval, and technical sanction.
Open
View answer
When estimating reinforced cement concrete (RCC) works, what cover assumptions are adopted: (i) at the end of a reinforcing bar, (ii) for thin slabs, and (iii) for longitudinal bars in a beam?
Open
View answer
In building measurement, damp-proof course (D.P.C.) installed in walls is measured for payment under which unit of measurement?
Open
View answer
In quantity surveying for civil engineering works, identify the incorrect rounding convention from the following measurement precisions (dimensions, areas, volumes, and weights).
Open
View answer
For earthwork in trenches or borrow pits, which statements correctly describe standard methods of measurement in uniform ground, irregular ground, and when direct methods are infeasible?
Open
View answer
In the long-and-short-wall method of estimation, the length of a long wall is taken as the centre-to-centre distance between walls plus which allowance?
Open
View answer
Practice smarter
Solve a few questions daily and revisit weak topics regularly to improve accuracy.