Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
2.0%
2.5%
4.0%
5.0%
Correct Answer:
5.0%
← Previous Question
Next Question→
More Questions from
Estimating and Costing
Pick up the correct statement regarding the centre line method of estimating a building
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended
The measurement is made for stone work in square metre in case of
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is
Pick up the correct statement from the following:
Berms are provided in canals if these are
According to Indian Standards Institute, the actual size of modular bricks is
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
Pick up the incorrect statement from the following:
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments