For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is
0.90 m3
0.94 m3
0.98 m3
1.00 m3
Correct Answer:
0.94 m3
← Previous Question
Next Question→
More Questions from
Estimating and Costing
The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, is
Pick up the correct statement from the following:
Berms are provided in canals if these are
According to Indian Standards Institute, the actual size of modular bricks is
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is
Pick up the incorrect statement from the following:
A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is
Pick up the correct statement from the following:
While estimating the qualities for the construction of a building, the correct metric unit is
The rate of an item of work depends on
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments