Productivity – Expected out-turn for a half-brick partition wall What is the typical expected out-turn (productivity) per mason per day for constructing a half-brick (about 115 mm thick) partition wall?
-
A1.5 m^3
-
B2.0 m^3
-
C4.0 m^2
-
D5.0 m^2
-
E6.5 m^2
Answer
Correct Answer: 5.0 m^2
Explanation
Introduction / Context:Expected out-turn helps planners estimate labour requirements, duration, and cost. For partition walls, productivity is measured by surface area (m^2) instead of volume, because thickness is standard and small.
Given Data / Assumptions:
- Half-brick wall ≈ 115 mm thick using common bricks.
- Average working conditions and normal course heights.
- Skilled mason with helper(s), typical 8-hour shift.
Concept / Approach:Industry thumb rules place half-brick masonry productivity around 4–6 m^2 per mason per day, depending on site factors. A commonly adopted nominal for planning is 5.0 m^2/day.
Step-by-Step Solution:Identify measure ⇒ area in m^2 for half-brick partitions.Adopt standard nominal value from schedule norms ⇒ 5.0 m^2/mason/day.Check plausibility against typical range (4–6 m^2) ⇒ within range.
Verification / Alternative check:Productivity norms in departmental handbooks commonly quote 5.0 m^2/day as a planning basis for half-brick partitions under average conditions.
Why Other Options Are Wrong:
- 1.5 m^3 and 2.0 m^3: incorrect unit (volume), not the conventional surface measure.
- 4.0 m^2: on the low side for average conditions.
- 6.5 m^2: optimistic and not a conservative planning value.
Common Pitfalls:Confusing m^2 with m^3 or using rates for full-brick masonry, which are significantly different.
Final Answer:5.0 m^2