In the shown project network (Activity-on-Arrow), the excavation activity starts at Event 1 and finishes at Event 2 (the arrow's tail and head).
Milestone charts (used to highlight key checkpoints in a schedule) were introduced historically around the year 1930.
In project scheduling terminology, the estimated time required to perform a specific activity is called its duration.
In construction planning, a time and progress chart is commonly referred to as a Bar chart (Gantt chart).
Identify the first widely used method for project planning: historically, the Bar chart (Gantt chart) preceded milestones, CPM, and PERT.
In scheduling, the difference between the time available to do a job and the time actually required for that job is called float (slack).
For a PERT activity with optimistic (to), most likely (tm), and pessimistic (tp) time estimates, the expected time t is computed as t = (to + 4*tm + tp) / 6.
Critical Ratio (CR) scheduling is a dynamic priority rule that compares time remaining with work remaining, thereby setting priorities, revealing status, and adapting as progress data change.
A Milestone chart highlights key checkpoints and can reveal delays or ahead-of-schedule achievements, but it does not depict detailed interdependencies among jobs.
In network planning for civil engineering projects, identify the incorrect statement about activities, events, nodes, and networks.
With total float = 5 days and original duration = 10 days for an activity, what schedule flexibilities are permissible without affecting the overall project?
In management history, Frederick W. Taylor introduced which influential organisational system for improving industrial efficiency?
In PERT, if a is the optimistic time, b is the pessimistic time, and m is the most likely time of an activity, what is the expected time (te)?
The technique specifically used to establish and maintain priority among competing jobs or work orders in a project or job shop is known as:
Select the correct comprehensive statement about CPM and PERT: orientation, uncertainty treatment, and time–cost linkage.
If TL denotes the latest allowable occurrence time of the head event, the total activity slack (total float) is equal to which of the following expressions?
According to standard public-works classification, works costing less than Rs. 20,000 are generally treated as which category?
On a bar (Gantt) chart for scheduling, individual activities of a project are conventionally represented by which graphical element?
In network analysis, the time by which an activity's completion can be delayed without affecting the earliest start of its immediate successor(s) is called:
In public works and civil engineering departments, the final technical authority for a project—covering drawings, specifications, and design approvals—vests with the Chief Engineer.