In the shown project network (Activity-on-Arrow), the excavation activity starts at Event 1 and finishes at Event 2 (the arrow's tail and head).
Open
View answer
Milestone charts (used to highlight key checkpoints in a schedule) were introduced historically around the year 1930.
Open
View answer
In project scheduling terminology, the estimated time required to perform a specific activity is called its duration.
Open
View answer
In construction planning, a time and progress chart is commonly referred to as a Bar chart (Gantt chart).
Open
View answer
Identify the first widely used method for project planning: historically, the Bar chart (Gantt chart) preceded milestones, CPM, and PERT.
Open
View answer
In scheduling, the difference between the time available to do a job and the time actually required for that job is called float (slack).
Open
View answer
For a PERT activity with optimistic (to), most likely (tm), and pessimistic (tp) time estimates, the expected time t is computed as t = (to + 4*tm + tp) / 6.
Open
View answer
Critical Ratio (CR) scheduling is a dynamic priority rule that compares time remaining with work remaining, thereby setting priorities, revealing status, and adapting as progress data change.
Open
View answer
A Milestone chart highlights key checkpoints and can reveal delays or ahead-of-schedule achievements, but it does not depict detailed interdependencies among jobs.
Open
View answer
In network planning for civil engineering projects, identify the incorrect statement about activities, events, nodes, and networks.
Open
View answer
With total float = 5 days and original duration = 10 days for an activity, what schedule flexibilities are permissible without affecting the overall project?
Open
View answer
In management history, Frederick W. Taylor introduced which influential organisational system for improving industrial efficiency?
Open
View answer
In PERT, if a is the optimistic time, b is the pessimistic time, and m is the most likely time of an activity, what is the expected time (te)?
Open
View answer
The technique specifically used to establish and maintain priority among competing jobs or work orders in a project or job shop is known as:
Open
View answer
Select the correct comprehensive statement about CPM and PERT: orientation, uncertainty treatment, and time–cost linkage.
Open
View answer
If TL denotes the latest allowable occurrence time of the head event, the total activity slack (total float) is equal to which of the following expressions?
Open
View answer
According to standard public-works classification, works costing less than Rs. 20,000 are generally treated as which category?
Open
View answer
On a bar (Gantt) chart for scheduling, individual activities of a project are conventionally represented by which graphical element?
Open
View answer
In network analysis, the time by which an activity's completion can be delayed without affecting the earliest start of its immediate successor(s) is called:
Open
View answer
In public works and civil engineering departments, the final technical authority for a project—covering drawings, specifications, and design approvals—vests with the Chief Engineer.
Open
View answer