If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Correct Answer:
← Previous Question
Next Question→
More Questions from
Construction Management
The technique for establishing and maintaining priorities among the various jobs of a project, is known
Pick up the correct statement from the following:
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
Works costing less than Rs. 20,000 are treated as
Various activities of a project, are shown on bar charts by
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
Final technical authority of a project lies with
Military organisation is known as
Critical Path Net Work helps an engineer
Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments