Pick up the incorrect statement from the following:
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these,
Correct Answer:
Bar chart establishes the interdependency of one event on another
← Previous Question
Next Question→
More Questions from
Construction Management
For completion of a project, the critical path of the network represents
Pre-tender stage requires
Frequency distribution curves
The first stage of a construction, is
Pick up the correct statement from the following:
Pick up the correct statement from the following:
Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Pick up the correct statement from the following:
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is