Pick up the correct statement from the following:
The difference of latest occurence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Construction Management
The main advantage of line organisation, is :
Pick up the correct statement from the following:
The main disadvantage of line organisation, is
Pick up the incorrect statement from the following:
For completion of a project, the critical path of the network represents
Pre-tender stage requires
Frequency distribution curves
The first stage of a construction, is
Pick up the correct statement from the following:
Pick up the correct statement from the following:
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments