Difficulty: Easy
Correct Answer: Activity
Explanation:
Introduction / Context:
Clear vocabulary prevents modeling errors in network schedules. CPM distinguishes work (activities) from milestones (events) and logic connectors (dummies).
Given Data / Assumptions:
Concept / Approach:
An activity represents work that takes time (duration) and may require resources. An event is a zero-duration point marking start/finish. A dummy is an artificial, zero-duration link to maintain logic or uniqueness in AOA networks. A contract is a legal instrument, not a scheduling element.
Step-by-Step Solution:
1) Map 'task performed' → work requiring duration → activity.2) Exclude event: marks completion/start without work.3) Exclude dummy: zero time, logic only.4) Exclude contract: legal/administrative, not a CPM element.
Verification / Alternative check:
CPM definitions universally define activities as the fundamental work units with durations and resource needs.
Why Other Options Are Wrong:
Common Pitfalls:
Final Answer:
Activity.