In CPM terminology, the performance of a specific, measurable task consuming time and/or resources is called an activity (events are milestones; dummies carry logic only).
-
ADummy
-
BEvent
-
CActivity
-
DContract
Answer
Correct Answer: Activity
Explanation
Introduction / Context:Clear vocabulary prevents modeling errors in network schedules. CPM distinguishes work (activities) from milestones (events) and logic connectors (dummies).
Given Data / Assumptions:
- We seek the term for 'performance of a specific task'.
- Options include dummy, event, activity, contract.
Concept / Approach:An activity represents work that takes time (duration) and may require resources. An event is a zero-duration point marking start/finish. A dummy is an artificial, zero-duration link to maintain logic or uniqueness in AOA networks. A contract is a legal instrument, not a scheduling element.
Step-by-Step Solution:1) Map 'task performed' → work requiring duration → activity.2) Exclude event: marks completion/start without work.3) Exclude dummy: zero time, logic only.4) Exclude contract: legal/administrative, not a CPM element.
Verification / Alternative check:CPM definitions universally define activities as the fundamental work units with durations and resource needs.
Why Other Options Are Wrong:
- Dummy: No work, no time—logic only.
- Event: Milestone node with zero duration.
- Contract: Commercial agreement, not a network component.
Common Pitfalls:
- Assigning duration to dummies (incorrect).
- Using events to represent work packages.
Final Answer:Activity.