The time which results in the leasi, possible construction cost of an activity, is known
normal time
slow time
crash time
standard time.
Correct Answer:
slow time
← Previous Question
Next Question→
More Questions from
Construction Management
Completion of an activity on CPM network diagram, is generally known
Site order book is used for recording
Critical path lies along the activities having total float
The object of technical planning, is
Construction team means
The main principle of an organisation, is
Henry Gantt developed Bar charts for planning and scheduling of projects in
An Executive Engineer may have powers upto
CPM is
Pick up the PERT event from the following:
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments