Difficulty: Easy
Correct Answer: all the above.
Explanation:
Introduction / Context:
Effective scheduling requires accurate inputs describing scope, productivity, and resource capacities. This question assesses understanding of the data categories required to develop a realistic construction schedule.
Given Data / Assumptions:
Concept / Approach:
A schedule links quantities to production rates to estimate durations and resource needs. Therefore planners need quantities of work, the number and sequence of operations, and productivity of both labour and equipment to compute durations and overlaps.
Step-by-Step Solution:
Step 1: Determine quantities for each work item (e.g., excavation volume, concrete volume).Step 2: Establish the list/number of operations forming the work breakdown.Step 3: Obtain labour output (units per day per gang) and machinery output (units per hour or day per machine).Step 4: Compute activity durations = quantity / production rate and build the network/bar chart.
Verification / Alternative check:
Cross-checking estimated durations with historical productivity data validates the schedule and supports resource leveling.
Why Other Options Are Wrong:
Common Pitfalls:
Using generic durations without grounding in actual quantities and production rates; ignoring equipment utilization or labour gang sizes.
Final Answer:
all the above.
Discussion & Comments