Critical path lies along the activities having total float
positive
negative
zero
same.
Correct Answer:
zero
← Previous Question
Next Question→
More Questions from
Construction Management
The object of technical planning, is
Construction team means
The main principle of an organisation, is
Henry Gantt developed Bar charts for planning and scheduling of projects in
An Executive Engineer may have powers upto
CPM is
Pick up the PERT event from the following:
The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A construction schedule is prepared after collecting
The salient feature of functional organisation is
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments