Difficulty: Easy
Correct Answer: All of the above
Explanation:
Introduction / Context:
CPM, or Critical Path Method, is a deterministic scheduling technique widely used in construction and infrastructure projects. It identifies the sequence of activities that determines the minimum project duration and highlights where schedule flexibility exists.
Given Data / Assumptions:
Concept / Approach:
CPM focuses on activities with known durations, calculates earliest and latest event times, and derives total float and free float. The “critical path” consists of zero-float activities that govern overall project duration.
Step-by-Step Solution:
Verification / Alternative check:
Standard scheduling texts differentiate CPM (deterministic, activity focus) from PERT (probabilistic). Both can be represented in AOA; the item specifically mirrors AOA CPM.
Why Other Options Are Wrong:
Any single statement alone is incomplete; only “All of the above” fully characterizes CPM per the question.
Common Pitfalls:
Confusing CPM with PERT; assuming CPM always uses AON (software may, but theory embraces both representations).
Final Answer:
All of the above