Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Home
»
Civil Engineering
»
Estimating and Costing
Pick up the correct statement from the following:
The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men
The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work
The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Estimating and Costing
In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and
According to ISI method of measurement, the order of the sequence is
The inspection pit or chamber is a manhole provided in a base drainage system
The most reliable estiamte is
The measurement is not made in square metres in case of
The expected out turn of 12 mm plastering with cement mortar is
The area of a sloping surface of a protective embankment of mean height d, side slopes S : 1 and length L is
Pick up the item of work not included in the plinth area estimate
If tensile stress of a steel rod of diameter D is 1400 kg/cm2 and bond stress is 6 kg/cm2, the required bond length of the rod is
The correct prismoidal formula for volume is
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments