For earthwork in trenches or borrow pits, which statements correctly describe standard methods of measurement in uniform ground, irregular ground, and when direct methods are infeasible?

Civil Engineering Estimating and Costing Difficulty: Easy
Choose an option
  • A
    In fairly uniform ground, measure using average depths between dead men (reference pegs).
  • B
    In irregular ground, determine quantities from the difference in levels before and after the work.
  • C
    Where neither (a) nor (b) is feasible, measure from the filling quantities after deducting voids.
  • D
    All the above.
  • E
    Only (a) and (b).

Answer

Correct Answer: All the above.

Explanation

Introduction / Context:Earthwork measurement varies with site conditions. Surveyors select techniques that best reflect actual excavation or filling. Understanding when to use average depths (dead men), level differences, or filling-based back-calculation ensures fair and auditable quantities.

Given Data / Assumptions:

  • Trenches or borrow pits can be in fairly uniform or irregular terrain.
  • Dead men (reference pegs) mark original ground to gauge average depths easily.
  • Filling-based inference is used only when direct measurement methods are impractical.

Concept / Approach:In uniform ground, average depths from fixed reference points give reliable volumes. In irregular ground, pre- and post-work levels yield volumetric differences. Where neither works (e.g., access constraints, waterlogged conditions), back-calculate from filled quantities and deduct voids to approximate the in-situ earthwork.

Step-by-Step Solution:Confirm A: Average depth method with dead men is standard for uniform ground.Confirm B: Level-difference (strip levels or grid) is appropriate for irregular ground.Confirm C: When direct measurement is infeasible, using fill with voids deduction is accepted practice.Hence D (All the above) is correct.

Verification / Alternative check:Field manuals outline all three as valid, with documentation of assumptions (e.g., bulking/void ratios) when using filling-based estimates.

Why Other Options Are Wrong:

  • E omits the legitimate third contingency approach and is therefore incomplete.

Common Pitfalls:Ignoring bulking/compaction factors; using the average-depth method in highly irregular ground.

Final Answer:All the above.

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion