Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Construction Management
Pick up the correct statement from the following:
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
Pick up the correct statement from the following:
PERT is
A goiden rule for the procurement of construction stones, suggests
Which one of the following represents an event?
For the execution of a project, a contractor is
The final selection of a construction site, is done by
Pick up the incorrect statement from the following:
For the network shown in the given figure, the expected time for the activity