Pick up the correct statement from the following:
Earliest expected time is denoted by TE
Latest occurrence time is denoted by TL
Contractual obligation time is denoted by Ts
Latest occurrence time is taken as contractual obligation time
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Construction Management
PERT is
A goiden rule for the procurement of construction stones, suggests
Which one of the following represents an event?
For the execution of a project, a contractor is
The final selection of a construction site, is done by
Pick up the incorrect statement from the following:
For the network shown in the given figure, the expected time for the activity
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Residential buildings are treated as
Railway projects are treated as
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments