Pick up the correct statement from the following:
The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
The float which affects neither the processor nor the successor activities, is called independent float
The difference between total float and free float, is called interfering float
All the above.
Correct Answer:
All the above.
← Previous Question
Next Question→
More Questions from
Construction Management
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
Pick up the correct statement from the following:
PERT is
A goiden rule for the procurement of construction stones, suggests
Which one of the following represents an event?
For the execution of a project, a contractor is
The final selection of a construction site, is done by
Pick up the incorrect statement from the following:
For the network shown in the given figure, the expected time for the activity
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is