Float concepts in CPM: Which of the following statements about total float, free float, independent float, and interfering float are correct?

Civil Engineering Construction Management Difficulty: Medium
Choose an option
  • A
    The duration between the earliest start of a preceding activity and the latest finish of a succeeding activity can be viewed as available float in the chain
  • B
    Free float is the time by which an activity can be delayed without affecting the start of any succeeding activity
  • C
    Independent float affects neither predecessor nor successor; it is the float available irrespective of other activities
  • D
    Interfering float equals total float minus free float
  • E
    All the above.

Answer

Correct Answer: All the above.

Explanation

Introduction / Context:Float (slack) quantifies schedule flexibility. Proper use of float helps level resources and absorb uncertainties without delaying project completion. Different float types serve different management purposes.

Given Data / Assumptions:

  • Total float TF = LS − ES = LF − EF.
  • Free float FF = min(ES of successors) − EF.
  • Independent float IF = max(0, ES of activity − LF of predecessor − duration).
  • Interfering float = TF − FF.

Concept / Approach:Total float measures how much an activity may move without affecting project finish; free float preserves successors; independent float is the portion independent of both predecessors and successors; interfering float is the portion that, if used, will delay the early start of successors but not the project finish.

Step-by-Step Solution:Confirm total float via ES/LS or EF/LF relations.Compute free float using successor earliest starts.Compute independent float using predecessor latest finishes and own ES.Find interfering float as the difference: TF − FF.

Verification / Alternative check:Network calculations should show TF ≥ FF ≥ 0 and IF ≥ 0 (by definition floored at zero). Critical activities have TF = FF = IF = 0.

Why Other Options Are Wrong:All listed statements align with standard CPM definitions; therefore 'All the above' is correct.

Common Pitfalls:Using free float where preserving successor early start is not required; double-counting float when multiple successors exist; forgetting that independent float can be zero even when total float is positive.

Final Answer:All the above.

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion