4. Pick up the incorrect statement from the following:
Options
A. The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
B. The difference between the maximum time available for the job and actual time it consumes, is called total float
C. The difference between the latest start time and earliest start time of an activity, is called total float
D. The difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity
Expected time = (Pessimistic value + 4*most likely value + Optimistic value)/6.
1-2 is 4.
2-3 is 7.
3-4 is 8.
6. Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is