  • 1. In the given figure, the network of a project represents
    Civil Engineering Construction Management: In the given figure, the network of a project represents

  • Options
  • A. activity of an excavation of a footing
  • B. activity of an excavation which starts at event No. 1 and ends at even No. 2
  • C. activity of excavation which takes 8 units of time
  • D. none of these.
  • Discuss
  • 2. Mile Stone charts were invented in the year of

  • Options
  • A. 1910
  • B. 1920
  • C. 1930
  • D. 1940
  • E. 1950
  • Discuss
  • 3. The estimated time required to perform an activity, is known as

  • Options
  • A. event
  • B. dummy
  • C. duration
  • D. float.
  • Discuss
  • 4. Time and progress chart of a construction, is also known as

  • Options
  • A. Bar chart
  • B. Gantt chart
  • C. Modified Mile stone chart
  • D. Critical path method chart
  • E. All the above.
  • Discuss
  • 5. The first method invented for planning projects, was

  • Options
  • A. Bar chart method
  • B. Milestone chart
  • C. Critical path method (CPM)
  • D. Programme Evaluation and Review Technique (PERT)
  • Discuss
  • 6. The difference between the time avail-to do a job and the time required to do the job, is known as

  • Options
  • A. event
  • B. float
  • C. duration
  • D. constraint.
  • Discuss
  • 7. If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

  • Options
  • A.
  • B.
  • C.
  • D.
  • E.
  • Discuss
  • 8. A critical ratio scheduling

  • Options
  • A. establishes the relative priorities among various activities on a common basis
  • B. determines the status of each activity
  • C. adjusts automatically changes in activity progress
  • D. is a dynamic system
  • E. none of these.
  • Discuss
  • 9. A Milestone chart

  • Options
  • A. shows the interdependencies of various jobs
  • B. depicts the delay of jobs, if any
  • C. points outgoing ahead of schedule of jobs, if any
  • D. none of these.
  • Discuss
  • 10. Pick up the incorrect statement from the following:

  • Options
  • A. The activity is the time consuming part of a project
  • B. The beginning and end of a job, are called events
  • C. The activity which consumes maximum time, is called a node
  • D. Logically and sequentially connected activities and events form a network
  • E. None of these.
  • Discuss