PERT (Program Evaluation and Review Technique) – managerial benefits Which statements describe what PERT provides to project management?

Difficulty: Easy

Correct Answer: All of the above

Explanation:


Introduction / Context:
PERT is a probabilistic network technique that models uncertain activity durations using three-point estimates to forecast likely project completion times and identify schedule risks.



Given Data / Assumptions:

  • Activities have optimistic, most likely, and pessimistic time estimates.
  • Dependencies among activities are known.
  • Management wants early warning of schedule variance.


Concept / Approach:
PERT computes expected activity times and variances, performs forward/backward passes, and yields a distribution for project duration. Continuous re-estimation enables rolling-wave updates.



Step-by-Step Solution:
Collect three-point times for each activity.Compute expected time te = (to + 4 * tm + tp) / 6 and variance = ((tp − to) / 6)^2.Find expected project duration and identify critical path.Monitor progress; update estimates; assess variation impacts quickly.



Verification / Alternative check:
Comparing forecast distributions to actual progress helps gauge realism of estimates and highlights where corrective action is needed.



Why Other Options Are Wrong:
PERT provides schedule insight first; cost can be integrated but is not its sole focus, so option (e) is incorrect.



Common Pitfalls:
Overconfidence in three-point estimates, ignoring resource constraints, or failing to update the network undermines PERT’s value.



Final Answer:
All of the above


Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion