Difficulty: Easy
Correct Answer: An activity
Explanation:
Introduction / Context:
CPM/PERT networks represent projects as connected elements. Distinguishing between activities, events, and durations is foundational to do forward/backward passes, compute floats, and identify the critical path.
Given Data / Assumptions:
Concept / Approach:
An activity is the performance of work that takes time and resources. An event (milestone) is a point in time indicating the start or finish of activities. Duration is the measured time an activity takes, not the work itself.
Step-by-Step Solution:
Verification / Alternative check:
Check glossary in project management standards: “activity” explicitly denotes the work to be performed.
Why Other Options Are Wrong:
Common Pitfalls:
Calling milestones “activities”; forgetting that dummy activities in AOA have zero duration and carry logic only.
Final Answer:
An activity
Discussion & Comments