PERT is
an analytic in concept
limited of event oriented diagrams
used for research and development projects
based on three time estimates for activities linking up two events
all the above.
Correct Answer:
all the above.
← Previous Question
Next Question→
More Questions from
Construction Management
A goiden rule for the procurement of construction stones, suggests
Which one of the following represents an event?
For the execution of a project, a contractor is
The final selection of a construction site, is done by
Pick up the incorrect statement from the following:
For the network shown in the given figure, the expected time for the activity
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Residential buildings are treated as
Railway projects are treated as
An event is indicated on the network by a number enclosed in
Discussion & Comments
No comments yet. Be the first to comment!
Name:
Comment:
Post Comment
Join Discussion
Discussion & Comments