Three men, four women and six children can complete a work in seven days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?
Open
View answer
A group of workers having equal efficiency can complete a job in 4 days. But it so happened that every alternate day starting from the second day, 3 workers are withdrawn from the job and every alternate day starting from the third day, 2 workers are added to the group. If it now takes 7 days to complete the job, find the number of workers who started the job.
Open
View answer
A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day? (N.M.A.T., 2006)
Open
View answer
If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work? (Bank Recruitment, 2010)
Open
View answer
8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? (Bank P.O., 2010)
Open
View answer
Sixteen men can complete a work in twelve days. Twenty-four children can complete the same work in eighteen days. Twelve men and eight children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work ?
Open
View answer
If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24 boys can do it in 4 days, then the ratio of the daily work done by a man to that of a boy is
Open
View answer
4 men and 10 women were put on a work. They completed $\frac{1}{3}$ of the work in 4 days. After this 2 men and 2 women were increased. They completed $\frac{2}{9}$ more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased? (M.A.T., 2006)
Open
View answer
One man, 3 women and 4 boys can do a piece of work in 96 hours, 2 men and 8 boys can do it in 80 hours, 2 men and 3 women can do it in 120 hours. 5 men and 12 boys can do it in :
Open
View answer
If 5 men and 3 women can reap 18 acre of crop in 4 days; 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days?
Open
View answer
X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in
Open
View answer
Directions: Each of the following questions consists of a question followed by three statements I, II and III. You have to study the question and the statements and decide which of the statement(s) is/are necessary to answer the question. In how many days A alone can complete a work? I. A and B can complete the work in 8 days. II. B takes twice the time taken by A in completing the work. III. A and B together take $\frac{1}{3}$ of the time taken by B alone in completing the work.
Open
View answer