A takes twice as long as B to finish a job, and C takes three times as long as B. Working together, they finish the job in 12 days. How many days would A take to do the job alone?
Ten men and eight women together complete a work in 5 days. One woman’s 1-day work equals half of one man’s 1-day work. In how many days will four men and six women complete the same work?
Five men started a job expected to be done in 15 days. After 5 days, 10 women joined them and together they finished in the next 5 days. If 10 women alone had started the job, in how many days would they have completed it?
A contract is to be completed in 50 days with 105 men working 8 hours per day. After 25 days, only 2/5 of the work is finished. If each man now works 9 hours per day, how many additional men are required to complete the work on time?
Fourteen men and twelve boys finish a work in 4 days, while eight men and sixteen boys finish the same work in 5 days. Compare the 1-day work of 1 man with that of 1 boy (expressed as a ratio of man to boy).
In a factory there are equal numbers of women and children. Women work 6 hours per day and children work 4 hours per day. During festival time, workload increases by 50%. By rule, children cannot work more than 6 hours per day. If women and children are equally efficient per hour and the extra work must be absorbed by women, how many extra hours per day must each woman work?
Three women and eighteen children together complete a work in 2 days. If six women alone can complete the same work in 3 days, then how many days will nine children alone take to finish the work?
A contractor plans to finish a work in 124 days with 120 men. After 64 days, 2/3 of the work is complete. How many men can be dismissed so that the work still finishes on time?
A contract must be finished in 92 days by 234 men working 16 hours per day. After 66 days, 4/7 of the work is completed. If each man now works 18 hours per day, how many additional men are needed to finish on time?
A, B, and C can finish a work in 16, 32, and 48 days, respectively. They all start together. A works until completion; C leaves 2 days before the work is finished; B leaves 1 day before completion. In how many days is the work completed?
Rashmi can complete a work in 16 days, Ravina in 12 4/5 (12.8) days, and Gitika in 32 days. They start together; Rashmi leaves after 4 days, and Ravina leaves 3 days before completion. How long does the work take in total?
A can do a piece of work in 10 days and B can do the same work in 15 days. They work together for 5 days, and the remaining work is completed by C alone in 2 more days. If the total wages for the whole work are Rs 3000, what are the daily wages of A, B and C respectively in rupees?
A, B and C can complete a piece of work in 24 days, 30 days and 40 days respectively when working alone. They begin the work together, but C leaves 4 days before the completion of the work. In how many days was the entire work completed?
Twelve men can complete a work in 8 days and sixteen women can complete the same work in 12 days. Eight men and eight women start the work together and work for 6 days. How many more men must be added so that the remaining work is finished in 1 more day?
P can complete a certain piece of work in 12 days working 8 hours per day. Q can complete the same work in 8 days working 10 hours per day. If P and Q work together, each working 8 hours per day, in how many days can they finish the work?
A and B together can complete a piece of work in 30 days, B and C together can complete it in 24 days, and C and A together can complete it in 20 days. All three work together for 10 days and then B and C leave. How many additional days will A alone take to finish the remaining work?
A can do a certain work in the same time as B and C together can do it. A and B together can complete the work in 20 days, and C alone can do the work in 60 days. In how many days can B alone complete the work?
A works twice as fast as B. If B can complete a piece of work in 18 days working alone, then in how many days can A and B together finish the same work?
A contractor employed a certain number of workers to finish a road within a scheduled time. After some time, he realised that at the current rate the work would be delayed by three-fourths of the scheduled time. He immediately doubled the number of workers and managed to finish the road exactly on schedule. What percentage of the work had been completed before he increased the number of workers?
A, B and C together can do a piece of work in 10 days. All three start the work together, but A leaves after 4 days. B and C together then complete the remaining work in 10 more days. In how many days can A alone complete the whole work?