Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Time and Work Questions
A can complete a piece of work in 30 days. He works alone on the job for 6 days and then B finishes the remaining work in 18 days. In how many days can A and B together complete the same work if both work at their usual rates from the beginning?
Amit can complete a piece of work in 45 days, while Bharath can complete the same work in 5 days less than Amit, that is, in 40 days. Amit and Bharath start the work together at their full efficiencies, but after working together for some days Bharath leaves. Amit then finishes the remaining work alone in 56 days, working at half of his usual efficiency during this period. For how many days did Amit and Bharath work together at full efficiency?
P alone can complete a piece of work in 24 days. The time taken by P to finish one third of the work is equal to the time taken by Q to finish half of the same work. How many days will P and Q working together take to complete the entire work?
Six men and eight boys can complete a piece of work in ten days, while twenty six men and forty eight boys can complete the same work in two days. In how many days will fifteen men and twenty boys together complete the entire work?
P and Q together can complete a job in 24 days. P alone can complete the same job in 32 days. If they work together for 8 days and then P leaves, how many additional days will Q alone take to finish the remaining work?
Arun works alone for 8 days and finds that only one third of the work has been completed. He then employs Akhil, who is 60 percent as efficient as Arun, and allows Akhil to complete the remaining work alone. How many more days will Akhil take to finish the remaining two thirds of the work?
Ten men can complete a certain piece of work in 15 days. If thirty seven men are employed instead, approximately how many days will they take to complete the same work, assuming all men work at the same constant rate?
Six men can complete a piece of work in 12 days, eight women can complete the same work in 18 days, and eighteen children can complete it in 10 days. Four men, twelve women and twenty children work together for 2 days. If only men are to complete the remaining work in 1 more day, how many men in total are required on that last day?
Four men and six women can complete a piece of work in 8 days, while three men and seven women can complete the same work in 10 days. In how many days will ten women working alone complete the entire work?
Twelve men can complete a certain piece of work in 9 days. After they have worked for 6 days, four more men join them. How many additional days are required to finish the remaining work after the new men join?
M can complete a piece of work in 10 days. N is 33.33 percent less efficient than M. How many days will M and N working together take to complete the entire work?
Four pipes P, Q, R and S can fill a cistern in 20 hours, 25 hours, 40 hours and 50 hours respectively. Pipe P is opened at 6:00 am, Q at 8:00 am, R at 9:00 am and S at 10:00 am. At what time will the cistern be completely full?
P is 30 percent more efficient than Q. How much time will P and Q working together take to complete a job that P alone could complete in 23 days?
Nine men and twelve boys finish a job in 12 days, while twelve men and twelve boys finish the same job in 10 days. In how many days will ten men and ten boys working together finish the job?
A contractor undertook to complete a certain work in 124 days and employed 120 men. After 64 days, he found that two thirds of the work was already completed. How many men can he discharge so that the remaining work is finished in exactly the originally planned 124 days?
Three athletes can complete one round around a circular field in 16 minutes, 24 minutes and 36 minutes respectively. If they start together from the same point and run in the same direction, after how much time will they all meet again at the starting point for the first time?
A contractor undertook a project that would normally take 20 days with 5 workers working continuously. The client asked for an earlier completion, so the contractor decided to add 5 additional workers every 2 days, starting from 5 workers on day one, in order to finish in the new time. Later, the total work was increased by 50 percent, but the contractor continued to add 5 workers every 2 days in the same pattern. How many more days, beyond the client's revised completion time, will now be required to finish the increased work?
A can build a wall in 16 days, while B can destroy the same wall in 8 days. A works alone for 5 days and then B joins A for the next 2 days. After that B stops, and only A works. In how many more days will A build the remaining part of the wall?
A and B are engaged to do a piece of work for Rs. 1540. A alone can do the work in 12 days and B alone can do it in 8 days. Working together with the help of C, they complete the work in 2 days. Assuming payment is divided in proportion to the amount of work done by each, what is the difference between the wages of C and B?
Time taken by P alone to finish a work is 50 percent more than the time taken by P and Q together. Q is three times as efficient as R. If Q and R together can complete the work in 22.5 days, then in how many days will P alone complete the work?
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27