Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Time and Work Questions
6 men + 8 boys finish a job in 10 days; 26 men + 48 boys finish the same job in 2 days. In how many days will 15 men + 20 boys finish it?
Sakshi can finish a job in 20 days. Tanya is 25% more efficient than Sakshi. In how many days can Tanya finish the same job?
A finishes a work in 18 days, B in 15 days. B works for 10 days and leaves. In how many days will A alone finish the remaining work?
A and B together finish a job in 30 days. A works alone for 16 days; B then finishes the remainder alone in 44 days. In how many days can B alone finish the whole job?
A, B, C can complete a work in 24, 6, and 12 days respectively. Working together, how long will they take to complete the work?
A can finish a job in 24 days, B in 9 days, and C in 12 days. B and C work together for 3 days; A completes the remainder. How many days does A take for the remainder?
A alone can do a job in 4 hours; (B + C) together in 3 hours; (A + C) together in 2 hours. How long will B alone take?
A completes 80% of a work in 20 days. A and B together finish the remaining work in 3 days. How long would B alone take to do the whole work?
A is 30% more efficient than B. If A alone can complete a job in 23 days, how long will A and B together take to finish it?
A and B can complete a work together in 30 days. They work together for 20 days; then B leaves, and A finishes the remaining work in the next 20 days. In how many days can A alone finish the work?
Average speed over equal distances: A traveler covers the first 160 km at 64 km/h and the next 160 km at 80 km/h. What is the average speed over the 320 km?
By walking at only three-fourths (3/4) of his usual speed, a person reaches his office 20 minutes later than he normally does. What is his usual (normal) time to cover the same route?
A man travels a total of 35 km partly at 4 km/h and partly at 5 km/h. If he instead travels the earlier portion at 5 km/h and the later portion at 4 km/h, he could cover 2 km more in the same total time. Find the original total time taken.
Six men or ten women can reap a field in 15 days. How many days will it take for a team of 12 men and 5 women to reap the same field?
Six children and two men complete a job in 6 days. Each child takes twice as long as a man to finish the work alone (i.e., a child is half as efficient as a man). In how many days can five men alone finish the same work?
Two men or five women or seven boys can finish a work in 469 days. In how many days will seven men, five women, and two boys together finish the same work?
A total of 314 weavers weave 6594 shawls in one-sixth (1/6) of an hour (i.e., 10 minutes). On average, how many shawls does one weaver weave per hour?
The efficiencies (work rates) of A, B, and C are in the ratio 6 : 5 : 4. If they receive a total of ₹ 27000 for completing the job and payment is distributed in proportion to individual work done, what is C’s share?
If two men or three women or four boys can complete a job in 52 days, then how many days will one man, one woman, and one boy together take to complete the same job?
A contractor planned to finish a project in 60 days. After 20 days, only one-fifth (1/5) of the work was completed with 75 workers employed. To finish on time, how many additional workers are required for the remaining 40 days (assume output is proportional to workforce)?
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28