Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Take Free Test
Time and Work Questions
Men–Women rate comparison: 16 men and 12 women together finish a work in 20 days. Separately, 18 women can finish the same work in 40 days. In how many days will 12 men and 27 women together finish the work?
Typing work with an interruption: A report of 100 pages is to be typed by three typists. Speeds: A types 100 pages in 10 hours, B in 20 hours, and C in 25 hours. All start at 09:00 a.m. At 01:00 p.m. (after 4 hours) A stops. B and C continue and finish the job. Approximately at what time is the report completed?
Men vs. boys productivity equivalence: 15 men can complete a work in 10 days, while 20 boys can complete the same work in 15 days. If 10 men and 10 boys work together, how many days will they take to finish the work?
Isolating one worker’s time from group times: Ganesh, Ram, and Sohan together can do a work in 16 days. Ganesh and Ram together can do the same work in 24 days. How long will Sohan alone take to complete the work?
A leaves mid-way – remaining work by A alone: A and B can complete a work in 8 days working together. B alone can do it in 12 days. After working together for 4 days, B leaves. How many days will A take to complete the remaining work?
After a joint start, one finishes the remainder: Ajay can do a work in 25 days and Sanjay in 20 days. They work together for 5 days, after which Ajay leaves. In how many days will Sanjay finish the remaining work alone?
Back-infer B’s solo time from a shortfall scenario: A and B together can complete a work in 3 days. They start together, but after 2 days B leaves. The work finishes 2 days later (i.e., after 4 days total). How many days would B alone take to complete the work?
After initial teamwork, B completes the remainder: A and B together complete a job in 24 days. A alone can complete it in 32 days. Both work together for 8 days and then A leaves. How many days will B take to finish the remaining work?
Equivalent work (man-hour balancing): 20 workers working 5 hours per day finish a job in 10 days. If instead 25 workers are employed for 10 hours per day, how many days will be required to complete the same job?
Meeting a deadline by releasing workers: 90 men are engaged to finish a job in 40 days. After 25 days, 2/3 of the work is complete. How many men can be released so that the remaining work is finished on schedule (i.e., within the original 40 days)?
Staggered team with A quitting early: A, B, and C can complete a work individually in 8, 12, and 15 days, respectively. A and B start together; after working for 2 days, A quits. Then C joins B and they continue till completion. In how many days (total) is the work finished?
A and B can complete a piece of work in 9 days and 18 days, respectively. However, due to illness, A is working at only 90% of usual efficiency and B at 72% of usual efficiency. If they work together at these reduced efficiencies, in how many days will the entire work be completed?
A job is planned for 36 men to finish in 48 days. After 24 days, only 2/5 of the work is completed. How many additional men must be employed so that the work is still finished within the original 48-day schedule?
Sixteen men working 18 hours per day can build a wall 36 m long, 4 m wide, and 24 m high in 20 days. How many men are required to build a wall 64 m long, 6 m wide, and 18 m high in 16 days if they work 12 hours per day?
A can finish a work alone in 5 days. With the help of his friend, the same work finishes in 3 days. In how many days can the friend alone complete the work?
A and B can complete a work alone in 15 days and 25 days, respectively. They start together, but B leaves after some time and A finishes the remaining work in the last 7 days. After how many days from the start did B leave?
A can complete a work in 20 days and B in 30 days. A works alone for 4 days, after which B and C together complete the remaining work in 18 days. In how many days can C alone complete the entire work?
Six men can finish a work in 12 days; eight women can finish it in 18 days; and eighteen children can finish it in 10 days. First, 4 men, 12 women, and 20 children work together for 2 days. If only men must finish the remaining work in 1 additional day, how many men are required?
A, B, and C can do a job in 18, 24, and 36 days, respectively. They work on alternate days in the order: Day 1 – C, Day 2 – B, Day 3 – A, Day 4 – C, and so on. In how many days will the work be finished?
Sixteen children and twenty-four men can finish a job in 18 days. If each child takes twice as long as each man to do the job alone (i.e., a child is half as efficient as a man), in how many days will 24 men finish the same job?
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28