More Questions from Time and Work

A contract is to be completed in 50 days with 105 men working 8 hours per day. After 25 days, only 2/5 of the work is finished. If each man now works 9 hours per day, how many additional men are required to complete the work on time?

Aptitude Time and Work Difficulty: Medium
Choose an option
  • A
    34
  • B
    36
  • C
    35
  • D
    37
  • E
    33

Answer

Correct Answer: 35

Explanation

Introduction / Context:When hours per day change mid-project, treat work in man-hours. Use completed fraction to infer total work, then determine the remaining workforce at new hours to meet the deadline.

Given Data / Assumptions:

  • Initial: 105 men, 8 h/day, 25 days → completed 2/5.
  • Remaining time: 50 - 25 = 25 days at 9 h/day.

Concept / Approach:Work W in man-hours. Compute W from the 2/5 completion, then solve M such that M*9*25 equals remaining 3/5 of W.

Step-by-Step Solution:

Initial man-hours = 105*8*25 = 21000 = 2/5 W → W = 21000*(5/2) = 52500Remaining = 3/5 W = 31500 man-hoursLet required men = M → M*9*25 = 31500 → M = 31500/225 = 140Additional men = 140 - 105 = 35

Verification / Alternative check:Check: 140*9*25 = 31500 → matches remaining workload.

Why Other Options Are Wrong:Off-by-one choices (34, 36, 37) test arithmetic; only 35 satisfies the exact equality.

Common Pitfalls:Forgetting to convert to man-hours after changing the daily hours.

Final Answer:35

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion