Difficulty: Easy
Correct Answer: Determines the detailed programme of start and finish times for operations (time-table of work)
Explanation:
Introduction / Context:
Within production planning and control, different functions have precise meanings. Confusing routing, scheduling, dispatching, and follow-up leads to poor coordination. This question checks whether you can identify the core role of scheduling.
Given Data / Assumptions:
Concept / Approach:
Scheduling creates the time-table. It fixes when each operation should start and finish on specific resources, subject to capacity constraints and due dates. Routing defines where work should go; dispatching releases work-orders; follow-up (or expediting) monitors actual progress against plan.
Step-by-Step Solution:
Verification / Alternative check:
Textbook PPC frameworks always depict scheduling as the time dimension, complementing routing (sequence) and dispatching (release).
Why Other Options Are Wrong:
(a) Routing concerns the route/sequence, not the calendar.(c) Dispatching triggers starts but does not plan times in detail.(d) Follow-up regulates progress and handles delays.(e) Time study sets standard times, not shop calendars.
Common Pitfalls:
Equating “sequence” with “schedule”; assuming dispatching is the same as scheduling.
Final Answer:
Determines the detailed programme of start and finish times for operations (time-table of work)
Discussion & Comments