The correct sequence of phases in value engineering is
creative phase, information phase, investigation phase, evaluation phase
information phase, creative phase, investigation phase, evaluation phase
investigation phase, information phase, creative phase, evaluation phase
creative phase, investigation phase, evaluation phase, information phase
Correct Answer:
creative phase, information phase, investigation phase, evaluation phase
← Previous Question
Next Question→
More Questions from
Industrial Engineering and Production Management
Micromotion study is
Dummy activities are used to
The type of layout used for manufacturing steam turbines, is
F. W. Taylor introduced a system of organisation known as
Two alternatives can produce a product. First has a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is
The planning and scheduling of job order manufacturing differ from planning and scheduling of mass production manufacturing.
An event is a function of two or more activities.
Product layout is best suited where
A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is
Follow-up prescribes the sequence of operations to be followed.