Difficulty: Easy
Correct Answer: Critical Path Method
Explanation:
Introduction / Context:
CPM is a fundamental technique in project management for planning, scheduling, and controlling complex projects by identifying the longest path of dependent activities that determines the minimum project duration.
Given Data / Assumptions:
Concept / Approach:
Critical Path Method computes earliest and latest start/finish times, floats, and identifies the critical path with zero total float. Managing critical activities prevents schedule slippage.
Step-by-Step Solution:
Verification / Alternative check:
Compare computed project duration with simulation or historical benchmarks; changes in any critical activity immediately change total duration.
Why Other Options Are Wrong:
Alternative expansions are nonstandard; CPM universally abbreviates Critical Path Method.
Common Pitfalls:
Ignoring resource constraints and assuming durations are fixed; in practice, resource leveling may alter the critical path.
Final Answer:
Critical Path Method